Lithuania proposes seven self-sufficient power zones and 10 new plants

Lithuania’s grid operator has opened consultations on seven emergency power zones, with plans for 800 MW of new capacity.

Transmission pylons, overhead cables and equipment at the Biruliškės electrical substation near Kaunas in Lithuania, 2011.
ARCHIVE — Biruliškės electrical substation near Kaunas, Lithuania, photographed in 2011. It is not one of the proposed new power plants.
Photo credit and license Photo: Vilensija / Wikimedia Commons, CC BY-SA 3.0; image from 5 August 2011, unchanged, depicts Biruliškės electrical substation near Kaunas, Lithuania. Not a new plant in the 2026 proposal. · Image source · License: Creative Commons Attribution-ShareAlike 3.0 Unported (CC BY-SA 3.0)
Text size

Lithuania has presented a plan to make its electricity system more resilient by allowing regions to operate independently during major emergencies. On 10 November 2026, transmission operator Litgrid launched a public consultation on a concept known as energy islands, in which portions of the national network could temporarily keep supplying power even if the main transmission system were disrupted.

The proposal envisages seven zones covering the country and roughly 10 new power plants with combined capacity of 800 megawatts. Lithuania's Energy Ministry says the additional facilities would support local electricity supply and rapid responses to network disturbances. Litgrid estimates construction costs of approximately €880 million, according to reporting by Reuters and Lithuanian news agencies. These are plans and estimated investments, not generating stations already built or contracts already awarded.

The implementation would take place in stages. Litgrid's published consultation sets out an initial phase between 2028 and 2033 covering the Vilnius, Kaunas, Klaipėda–Mažeikiai and Šiauliai–Panevėžys regions. From 2033, the operator envisages at least seven zones across Lithuania. The public consultation remains open until 10 December 2026, providing an opportunity for market participants to examine the proposed technical and commercial arrangements.

The design reflects concern that damage to key network equipment, cyberattacks, sabotage or extreme weather could interrupt electricity supplies over a broad area. If regions can be isolated and supported by local generation, a failure in one part of the system need not automatically cause the same scale of disruption elsewhere. Litgrid wants plants able to start rapidly and operate when wind and solar output is insufficient.

The choice of generation technology is not settled. Litgrid's chief executive told Reuters that gas was an obvious candidate because of the required operational flexibility, but that procurement would not prescribe a particular technology. This raises a policy trade-off with Lithuania's objective of climate neutrality by 2050. The forthcoming consultation and tenders will determine how the resilience concept is turned into actual projects, their costs and their energy mix.